The Woonsocket, R.I., City Council approved a resolution Nov. 23 to settle a lawsuit filed by the state in March 2023 over sewage discharges from the city's regional wastewater treatment plant. The $1 million settlement comes as the city considers the future of a sludge incinerator serving approximately 30 communities.
The lawsuit alleged that the regional facility discharged partially untreated sewage into the Blackstone River.
Under the settlement terms reported by WPRI, private contractors Jacobs Engineering and Synagro Woonsocket will each pay $250,000, a combined $500,000 in fees and environmental program funding. An additional $500,000 in penalties will be suspended if the contractors and the city comply with state requirements, including new reporting and operational obligations.
City Council President and Mayor-elect Dan Gendron said the contractors must install a warning system to help prevent future discharges and promptly report potential violations. Gendron attributed the three discharges at the center of the lawsuit to the treatment facility becoming overwhelmed.
The settlement comes amid broader changes at the facility. Veolia was brought in to temporarily manage wastewater treatment operations in September after Jacobs ended its 20-year contract.
Woonsocket's mayor-elect wants to close the facility's sludge incinerator by June 30, 2027. The city estimates that upgrading the incinerator would require between $40 million and $50 million. A closure could require communities that rely on the facility to identify alternative biosolids management and disposal options.
While the City Council has approved the resolution, the status of final state approval, the timeline for installing the warning system and the long-term future of the incinerator have not been confirmed.